Global Utilities

Waterless Urinals

Purpose

Improve the Universities water efficiency.

Reason for the project

To provide a physical presence for La Trobe’s water saving initiatives.

Funding

Major maintenance.

Work Details

  • Remove existing flushing urinals and cap off flusher system.

  • Install new urinals.

  • Remove new urinals and reconstruct pipe work infrastructure.

  • Re install urinals.

Construction Period

  • First part 14/06/2008.

  • Second part to take place with toilet upgrade 27/7/2008 to 20/8/2008.

Project Manager

Peter Foulds
Maintenance Manager

Back to List

Content Approved by: Director, Buildings and Grounds Division
Page maintained by: Systems Administrator (Sehmeet Singh)
Last Updated: 11 February, 2008