Global Utilities

Student Hub project

Purpose

A new Student Hub will be created and will combine all non-academic student services into a single building to be constructed on the ground floor of the Thomas Cherry Building at the entry to the “student axis” on the Bundoora campus. The building will centralise a range of student services including enrolment, legal and financial services, counseling, advocacy, transport services and accommodation sourcing. The new facility will also include a student lounge, project spaces and study facilities.

This project will bring together scattered elements of administrative staff providing support and advice to students to the one, centrally accessible location and also provide study & learning space for students in a prominent ground level location on campus.

The benefits of this component will be giving the student community a more streamlined and effective provision of face-to-face support services in the one location and additional semi-formal and informal study space on campus. This collocation of service provisions and informal space enables the student services to expand in times of peak demand into the study space, and then contract back during the bulk of the term when students require a range study locations.

Funding

The Student Hub Project is fully funded from the Better University Renewal Fund (BURF) in the amount of $4.58 million.

Work Details

The work involves the complete refurbishment of level 1 of the Thomas Cherry Building.

To allow this refurbishment, there are a number of decanting stages which are necessary. These will be undertaken as a separate contract during 2009 with a completion date of 15 Feb 2010.

Construction Period

Project phase
Start date
End date

Brief and Schematic Design

16th, Jan 09

29th, May 09

Design and documentation

2nd, June 09

15th, Oct 09

Tender and award

16th, Oct 09

30th, Nov 09

Preliminary Works and mobilisation

1st, Dec 09

15th, Feb 10

Main Construction

16th, Feb 10

16th, Dec 10

Fitout and FF&E

16th, Oct 10

16th, Dec 10

Total

16th, Jan 09 (Project starts)

16th, Dec 10 (Project complete)

Project Manager

Jim Colebatch
Deputy Director - Special Projects

Back to List

Content Approved by: Director, Buildings and Grounds Division
Page maintained by: Systems Administrator (Sehmeet Singh)
Last Updated: 11 February, 2008